Monitoring: What Are the Reasons Why Schools Are Not Ready for the New Academic Year on Time?
Uzbekistan’s Development Strategy envisages the establishment of 1.2 million new educational places by 2026. In order to achieve this goal, in 2022, construction and repair works were carried out in 791 schools, and 120 000 new student places were created. In addition, the state program 2023 envisages the establishment of 76,000 new student places by means of construction of 237 new schools. These goals show that reforms in the field of education keep relevance in our country.
This August, the Nationwide Movement "Yuksalish" studied preparations for the 2023/2024 school year in 122 schools throughout the republic by conducting public monitoring. During the monitoring, experts studied the timeliness and quality of construction and repair works in schools, and the condition of classrooms.
Checking the readiness of 57 schools for the new academic year, it was found that all construction and repair works were carried out on time and with high quality, and they are ready for the new academic year.
It was found that 65 schools are not fully ready for the new academic year
At the same time, it was found out that 65 schools are not fully ready for the new academic year. 10 of these schools are not provided with the necessary equipment, and 55 of them have not completed construction and repair works. 12 of them are under construction, 32 are under reconstruction, and 11 have not completed overhaul.
For example, in the 14th general education school located in the Sh.Rashidov district of the Jizzakh region, the construction of a new educational building for 330 seats has not been completed. Although, reconstruction work was completed in the 31st general education school located in Uzbekistan district of Fergana region, it was not provided with the necessary equipment and facilities. Despite the fact that the 21st general education school located in Pakhtachi district of Samarkand region has been reconstructed, it was found out that the heating systems of the school are in critical condition and the school kitchen is equipped for only 70 seats. It was found that the construction of a new building with 240 seats and a sports hall in the 28th general education school in the Gulistan district of the Syrdarya region was not completed by the beginning of the new academic year. The construction work has stopped due to the fact that the necessary funds for the construction of the new building of the 336th general education school located in the Yangihayot district of Tashkent have not been allocated to the contracting organization by the "Single Customer Service" Engineering Company.
In many cases, construction organizations have not completed work by the deadline, tenders were held late, and financing is delayed.